A personal fall arrest system (FAS) is a system designed to minimise injury if a worker should fall from a significant height and experience impact. The purpose of the system is not to stop the fall (that is the purpose of a fall restraint system or fall prevention system), but to limit the injuries that could happen to a worker as a result of the fall's impact.
Fall arrest systems can be permanently installed. They can be used during recurring height related tasks (such as window cleaning, gutter work or regularly scheduled maintenance).
This system is made up of components that may include a body harness, an anchor, a connector, a lanyard, a deceleration device and a lifeline.
These systems must be professionally installed and should be regularly inspected to ensure compliance with health and safety and CDM regulations (Construction Design and Management) regulations. These can be internal inspections carried out by the contractor, third party audits or external inspections by the Health and Safety Executive.
Fall arrest systems should be replaced when necessary. Training is required for proper usage.
Personal fall arrest systems are most commonly used in situations where a fall is possible and a collective restraint system or fall prevention system is not in place.
[edit] Related articles on Designing Buildings Wiki
- BS 7883.
- BS 7883 guide released.
- Collective restraint systems.
- Dynamic self-retracting lanyard.
- Fall prevention systems.
- FASET.
- Hoists.
- Injuries on construction sites.
- Personal fall protection system.
- Safety in high places.
- Safety systems for working at heights.
- Site safety.
- Work at height checklist for managers.
- Work at height regulations.
- Work at height.
- Working at height - our duty to prevent harm and protect each other.
- Working at height training.
[edit] External resources
- Health and Safety Executive, A technical guide to the selection and use of fall prevention and arrest equipment, 2005.
- Health and Safety Executive, Inspecting fall arrest equipment made from webbing or rope, 2009.
- Health and Safety Executive, The Construction (Design and Management) Regulations 2015, 2015.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Recognition, influence and growth
SocEnv identifies three strategic pillars in new strategy to 2045.
Discover the future of roofing, cladding and insulation.
New guidance for professional practice, cultural change and regulation in social housing.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.